September 11, 2023
A Look at Spoliation Remedies in Florida
Spoliation of evidence can make or break any case, regardless of how strong liability and damages may be. As a firm with an entire division dedicated to litigating subrogation matters, we have been on both ends of spoliation motions. This shall serve as a synopsis of how Florida handles spoliation in various scenarios.
August 31, 2023
The State of the Statute of Repose in the State of New York
New York is famous for not having a Statute of Repose of any sort. For the purposes of this discussion, a Statute of Repose bars a claim against design professionals and contractors after passage of a certain amount of time from project completion. This is different than a Statute of Limitations, which sets a deadline to commence a lawsuit measured from the time of the loss or injury. The rationale behind the Statute of Repose is to allow design professionals and contractors to put a project to rest, at some point. For example, if doors are jammed 25 years after construction, the owner should not be able to make a claim against those that did the design and construction of the entire building. New York and Vermont are the only two states remaining with no Statute of Repose.
Under the current law in New York, contractors and design professionals are exposed to claims for personal injury and property damage resulting from construction defects for an unlimited number of years after a project is completed. New York Civil Practice Law and Rules (“CPLR”) Section 214-d is sometimes referred to as the mini-Statute of Repose. Section 214-d requires wrongful death, personal injury, and property damage claimants to serve design professionals with a written notice of claim, at least ninety days prior to commencement of a lawsuit, when the design or construction work was completed more than ten years prior to the date of the claim. Failure to serve the notice sets the stage for a motion to dismiss pursuant to CPLR § 3211(h) or CPLR § 3212(i). If the defendant can show that more than ten years have passed since the project was completed, and no notice was served, the case will be dismissed. See, Dorst v. The Eggers Partnership, 265 A.D.2d 294, 696 N.Y.S.2d 478 (2 Dept. 1999). This mini “Statute of Repose” is something of a joke. Among other things, even if a claim is dismissed for failure to serve the ninety-day notice, all that the claimant needs to do is serve the notice and start a new action.
New York is revered to be the financial capital of the world, as well as a center of art, fashion, music, theater, media, innovation, and progress. As the law is currently written, design professionals and contractors in New York are subject to claims for an indefinite period of time. After 10 years a claimant must serve a notice, but this could be 20, 30, 50, or more years after the project is completed. This creates a lot of uncertainty for design professionals and contractors and their liability insurers. This must be balanced against the need and expectation by building owners and the public that buildings remain safe and usable structures beyond the 10 years or less that most other states have adopted for their statute of repose.1
The design and construction communities in New York have been lobbying for a Statute of Repose for many years, and now there are bills pending in the New York State Assembly and Senate to repeal CPLR § 214-d in its current form and replace it with a 10-year Statute of Repose for personal injury, wrongful death, and property damage claims asserted against design and construction professionals. In this regard, the Assembly’s Standing Committee on Higher Education and the Senate’s Judiciary Committee, each have been considering a bill (Assembly Bill A35952 and Senate Bill S412723) to impose a limitations period of ten years after the completion of improvements to real property. The bill has had no action for more than a year. A primary motivating factor for the bill, cited by the New York Legislature, is that the purpose of the bill is to curb the continuing rise in insurance premiums by bringing certainty to the scope of post-operational risk to which design professionals and contractors are exposed. In an effort to be fair, each bill provides for a one-year extension to serve a notice of claim, which accrues during the tenth year after the completion of the improvements.
In New York, and even more so in New York City, buildings are expected to last 50 or more years. We do not want the facades of 20-year-old buildings falling to the sidewalk with no recourse to the designers and builders responsible for the failure. We do not want a fire sprinkler main line to fail causing millions of dollars in property damage and endangering the lives of thousands of people.
1A table of the various statutes of repose in the 50 United States can be found here
2The text of the proposed Assembly Bill can be found here
3The text of the proposed Senate Bill can be found here
August 14, 2023
Waiving Consequential Damages – The Struggle Continues
Consequential damages waiver clauses are found in almost all standard construction industry contracts. Not surprisingly, parties want to avoid the economic impacts of unforeseen consequences. Yet all too often, we find ourselves litigating over the enforceability of consequential damages waivers because the confusion about these clauses is so widespread. Why are these boilerplate standard waivers so problematic? The two main reasons are: 1) nobody can agree on what consequential damages are; and 2) the consequential damages waivers are often ambiguous.
So, what exactly are consequential damages? The term seems pretty straight forward, but if you’ve been an attorney long enough, you know that very little is black and white. We are experts at navigating gray areas, and, as if to recognize the need for guidance, Florida courts provided us with a roadmap to assist us in analyzing damages by dividing them into 3 categories: general, special, and consequential.
General Damages
General damages are those which naturally flow or result from the injuries alleged. They are commonly defined as those damages that are the direct, natural, logical, and necessary consequences of the injury. For example, let’s say Bob hires Joe to repair his AC unit and pays Joe $3,000 in exchange for Joe’s performance of the repair. If Joe breaches the contract by failing to repair the AC unit, Joe owes $3,000 to Bob in general damages.
Special Damages
Special damages are monies that will compensate a plaintiff for damages that do not normally result from a breach. To recover special damages, the plaintiff must prove that when the parties made the contract, the defendant knew or reasonably should have known of the special circumstances leading up to such damages. They consist of items of loss that are peculiar to the party against whom the breach was committed and would not be expected to occur regularly to others in similar circumstances. Let’s take things a little further in our example above with Bob and Joe. Bob told Joe that he needed his AC unit to be repaired because his grandmother who lives out of state planned to visit him next week and could not stay at his home if the AC was not working. Joe told Bob the repair would be simple and could be completed in a few hours on Monday morning. Monday morning just so happened to be the day that Bob’s grandmother was to arrive. Joe breached the contract by failing to perform the repair, and Bob had to pay for his grandmother to stay in a hotel during her visit. The cost of Bob’s grandmother’s hotel stay would be considered special damages because the loss is peculiar to Bob and his circumstances.
Consequential Damages
The distinction between consequential damages and general damages lies in the loss incurred by the non-breaching party in its dealings with third parties. “Consequential damages do not arise within the scope of the parties’ transaction, but rather stem from foreseeable losses incurred by the non-breaching party in its dealings, often with third-parties, such as costs of repair.” In Keystone Airpark Authority v. Pipeline Contractors, Inc, 266 So.3d 1219 (Fla. 1st DCA 2019), the First District relied on several cases throughout the country that illustrated the differences between consequential damages and general damages. In Urling v. Helms Exterminators, Inc., 468 So.2d 451 (Fla. 1st DCA 1985), the First District found that the cost to repair extensive termite damage to a home purchased after a termite inspection company erroneously certified that the home was free of damage constituted consequential damages, whereas the cost of the termite inspection constituted actual damages. The Eastern District of Virginia found that a property owner’s cost to correct structural defects that resulted from defective plans prepared by an architect constituted consequential damages. The Eastern District of Virginia also found that the cost to repair a leaking roof caused by an architect’s defective plans constituted consequential damages. While the differences among the three categories of damages may not be clear cut, Keystone provides a general framework that serves as a helpful guide.
How can a consequential damages waiver clause be ambiguous? Florida Courts allow parties to limit their remedies, including their liability for consequential damages so long as the terms of the contract are clear and unambiguous. Courts have found consequential damages waiver clauses to be ambiguous and unenforceable when the clause’s language was unclear as to the circumstances to which it applied.
Take the following example:
“Owner releases, and agrees that Contractor will not be held liable for any damages to the premises, nor for loss or damage, consequential, incidental or direct, including but not limited to any: theft, vandalism, wind; storm, rain, fire, flood; lightning strikes, force majeures; owner’s moving, eating or rental expense or income; disruption of services including utilities. In the event that any work performed by Contractor is wholly or partially destroyed or damaged due to theft, vandalism; wind; storm; rain; fire; flood; lightning strikes; force majeure or any other causes not under Contractor’s control, the loss shall be sustained by Owner and shall not be the responsibility of the Contractor.”
The contractor will argue that this waiver clause deals with two aspects of damages; 1) damage to the premises; and 2) damages to the contractor’s work. The first sentence arguably means that the contractor is not liable for any damages to the premises, regardless of whether those damages are considered direct or consequential and regardless of the source. The second sentence deals with damage to the contractor’s work and provides that the Owner will be responsible for the loss if the work is damaged by circumstances outside the contractor’s control. The owner, however, will argue that the waiver is ambiguous and contradicts itself.
Owner on the other hand, will argue that there is a direct conflict between the first and second sentence because the first sentence absolves the contractor from liability for damages to the property, while the second only absolves the contractor from liability in the event the damages to the premises are outside of contractor’s control, and that the “premises” arguably includes the contractors’ work.
Another example is:
“The Consultant and Owner waive consequential damages for claims, disputes, or other matters in questing arising out of or relating got this Agreement. This mutual waiver is applicable, without limitation, to all consequential damages due to either party’s termination of This Agreement.”
While this clause from the outset may appear to bar the Owner’s consequential damages claims against the consultant in a potential breach of contract claim, the second sentence calls into question the applicability of the waiver. The second sentence could be interpreted to mean that the only consequential damages that are waived are those that arise following termination. The clause’s ambiguity runs the risk of rendering it unenforceable.
You can avoid the consequential damages waiver pitfalls by: 1) educating yourself on what consequential damages are; 2) drafting well written clauses that are not potentially self-contradictory nor open to multiple interpretations; and 3) listing out the damages that are being waived, i.e. lost profits, increased labor and material costs, rental expenses, loss of use, etc. Acquiring a deeper knowledge and understanding of what consequential damages are will allow you to better draft an enforceable consequential damages waiver clause for your client’s benefit.
[1] Hardwick Properties, Inc. v. Newbern, 711 So.2d 35, 39 (Fla. 1st DCA 1998) quoting Hutchinson v. Tompkins, 259 So.2d 129 (Fla. 1972)
[1] Keystone Airpark Authority v. Pipeline Contractors, Inc. 266 So.3d 1219 (Fla. 1st DCA 2019) citing to Fla. Power Corp v. Zenith Indus. Co 377 So.2d 203, 205 (Fla. 2d DCA 1979)
[1] Hardwick Properties, Inc. v. Newbern, 711 So.2d 35, 39 (Fla. 1st DCA 1998) citing to Jonson v. Monsanto Co, 303 N.W. 2d 86 (N.D. 1981)
[1] Keystone Airpark Authority v. Pipeline Contractors, Inc. 266 So.3d 1219 (Fla. 1st DCA 2019)
[1] Keystone Airpark Authority v. Pipeline Contractors, Inc. 266 So.3d 1219 (Fla. 1st DCA 2019) citing to Urling v. Helms Exterminators, Inc. 468 So.2d 451 (Fla. 1st DCA 1985) and to Bartram, LLC v. Landmark Am Insurance Co., 864 F. Supp. 2d. 1229, 1240 (N.D. Fla. 2012)
[1] Keystone Airpark Authority v. Pipeline Contractors, Inc. 266 So.3d 1219 (Fla. 1st DCA 2019) citing to Fed. Reserve Bank of Richmond v. Wright 392 F. Supp. 1126, 1131 (E.D. Va 1975)
[1] Keystone Airpark Authority v. Pipeline Contractors, Inc. 266 So.3d 1219 (Fla. 1st DCA 2019) citing to McCloskey & Co., Inc. v. Wright, 363 F. Supp. 223 (E.D. Va. 1973)
[1] Amoco Oil, Co. v. Gomez, 125 F. Supp. 2d 492 (S.D. Fla. 2000)
[1] Orkin v. Montango, 359 So.2d 512 (Fla. 4th DCA 1978).
July 17, 2023
Does Fla. Stat. 768.0427 Apply to Medical Damages Presented to the Jury in Lawsuits Filed Before March 24, 2023?
DSBC Associate Katie Hinkle explores whether or not Fla. Stat. 768.0427 applies to medical damages presented to the Jury in lawsuits filed before March 24, 2023.
April 24, 2023
Sufficiency of Affidavits Supporting Motions for Summary Judgement
Motions for Summary Judgment are a useful tool for insurance companies to have a Court rule on issues in a case as a matter of law before those issues are presented to a jury. DSBC Associate Marni Rogalsky breaks down its use in the context of defending first-party property cases.
January 10, 2023
Letters of Protection: Effective “I Owe Yous” or Evidence of Failure to Mitigate Damages
Learn about the advantages and disadvantages of a Letter of Protection from the legal experts at DSB&C.
October 12, 2022
Learning to Love Massachusetts Superior Court Rule 9A (Pt. II – Summary Judgment)
Massachusetts Superior Court Rule 9A is often the bane of many attorneys due to its length, complexity, and specificity. This blog post is a guide to filing/serving Summary Judgment Motions in the Superior Court.
January 31, 2022
Wielding the Double-Edged Sword of Non-Binding Arbitration
Many, if not all, Uniform Trial Orders include a mediation requirement. Increasingly, some judges have also been uniformly ordering cases to non-binding arbitration as an alternative method of resolution. Non-binding arbitration can be both a blessing and a nuisance.